100MW Wind Power Plant Project at Feni

Search

 

  • Approval
  1. Administrative approval on 08.07.2015
  2. Governmental approval on 31.05.2015
  • Land Acquisition
  1. Field book entry was completed on 28.02.2016
  2. LA proposal was sent to Land Ministry from DC office, Feni on 05.05.2016
  • DPP for land Acquisition

Project Evaluation Committee (PEC) meeting on Recast DPP for Land acquisition held on 29/05/2016. Recast DPP was sent to Power Division on 27.06.2016

  • Feasibility Study

Power Cell revised 30 Nos. of proposals in response to REOI for Feasibility Study. The Proposals are under evaluation.

  • Financing

EGCB Board decided to implement the project through competitive ECA financing.